Construction of a 50 MW wind farm in the Karakiya district of Mangystau region
Energy
Funding status: Guarantee status: On financing
Information about Sarkylmas Kuat LLP
| Project name | Construction of a 50 MW wind farm in the Karakiya district of Mangystau region | |||
| Project description |
|
|||
| Borrower Development Bank of Kazakhstan JSC |
Sarkylmas Kuat LLP |
|||
|
Final beneficiaries |
Nan Yi, Nan Haoren, Zhandosov Oraz, Kozhasbay Erlan | |||
| Product | Electricity | |||
| Structure of project financing | Project cost | 212 mln ¥ / 14,755 bln ₸ | ||
| Participation of Development Bank of Kazakhstan JSC, in the context of financing currencies |
122.796 mln ¥ / 8.546 bln ₸
|
|||
|
Borrower's own participation |
89.203 mln ¥ / 6.208 bln ₸ | |||
|
|
|
|||
| Terms of granting the financing instrument of Development Bank of Kazakhstan JSC | Funding currency | Chinese Yuan | ||
| Type of financing instrument | Non-revolving credit line | |||
| Rate of remuneration |
5Y LPR + 0,93% per annum, floating
|
|||
| Loan term | Up to 108 months from the date of conclusion of the Agreement on opening a credit line | |||
| Funding source | Other sources of the Bank (attracted funds) | |||
| Additional Information | Address |
Legal address: Republic of Kazakhstan, Mangystau region, Karakiya district, Munayshi village, Novostroika microdistrict 7/2, postal code 130305; Actual address (office): Republic of Kazakhstan, Almaty, Medeu district, Dostyk Avenue 192/2, postal code 050051 |
||
| Tel. |
+7 727 357 77 77 |
|||
|
|
|
|||